New CS Buildings
This page contains information on buildings built over the past 10 or so years by other Computer Science Departments.
It is meant as an aid to the planning process for the new "Gates Center for Computer Science".
A PDF summary of the information on this page.
# MIT, 2004
Stata Center: the William H. Gates Building and the Alexander Dreyfoos Building
Also see the book "Building Stata" by Nancy Joyce, the project director
Project Cost: Original goal was $212 million, current projection is $285 million (see discussion)
Construction Cost: $198 million for "core and shell"
Space: 420K GSF + 280K GSF Parking
Dryefoos tower: AI, Lab for Inf. and Decisions Systems (LIDS), Linguistics and Philosophy Dept.
Gates tower:LCS
Ground level:"student street", food services, child care center (73 children)
Basement:atheletic facility: fitness, dance, locker room, access to Alumni pool
Plans: HTML or PDF
Major Donors: $25M Ray Stata, $15M Alexander Dreyfoos, $20M William Gates (more info on donors)
Architect: Frank O. Gehry
# UIUC, 2004
Siebel Center
Project Cost: $80 million (original projection, final cost?)
Construction Cost: $55 million ($245 GSF)
Space: 225K GSF, 128K ASF (17K Lower, 27K 1st, 29K 2nd, 28K 3rd, 28K 4th).
Undergrad: 29K = 9K Labs, 8K Classrms, 4K Lecture Hall, 7K TAs
Research: 11K Labs, 23K Faculty Offices, 19K RAs
Support: 46K = 3K Acad, 3K Admin, 3K Busin., 11K Conf + Fac support, 8K Comp rooms, 2.4K Mail/Ship, 8K Atrium + Lounge, 2K Storage
Major Donors: $32M Thomas M. Siebel
Architect: Bohlin Cywinski Jackson (design), LZT (architect)
# UCSD, 2004
Computer Science and Engineering Building (EBU3b)
Project Cost: $41-45 million
Construction Cost: $30 million ($205/GSF)
Space: 148K GSF, 87K ASF (12K Basement, 19K 1st, 19K 2nd, 19K 3rd, 18K 4th), 137K BOMA rentable
150 offices, 11 conference rooms, 100 person lecture hall
2K admin. offices, 2K admin support, 2K student affairs, 12K instructional, 17K research offices, 20K research labs, 8K research support, 3K stor./print/kitchen, 5K conference rooms, 5K Computer support.
10K Warren College (University Administration)
The department has about 50 tenure faculty, 10 lecturers, 10 researchers, 20 visitors, 10 research staff, 25 administrators/assistants, 160 PhD students, 120 Master's students
Plans: Basement, 1st Floor, 2nd Floor, 3rd Floor, 4th Floor
Project Planning: Detailed description of the planning process.
Major Donors: none given, but building is yet to be named
Architect: Bohlin Cywinski Jackson (design)
# U. Washington, 2003
Paul G. Allen Center
UWs "top institutional priority"
Project Cost: $72 million, includes renovating part of adjacent building
Construction Cost: $44 million including renovation ($245/GSF)
Space: 168K GSF, 85K ASF (+ 22K GSF renovation)
Plans: html
Major Donors:
$7.2M Microsoft, $14M Paul Allen, $6.5M Bill and Melinda Gates Foundation, 7 other $1M+ gifts, 75 other $25K+ gifts.
$42M was from private giving, $20M from UW, $10M from state.
The Gates foundation has also given/pledged $70 Million torwards a new $150M building for Genomics research (2003), and $12 Million to a new law building Gates Hall (named after Bill Gates' father).
Bill Gates has also given $10 million for renaming the Physics building Mary Gates hall (1995), and $12 Million too launch the department of Molecular Biotechnology in the School of Medicine (1992).
Dedication ceremony: Oct 9, 2003
Hank Levy, faculty liaison for Allen Center design and construction
Architect: LMN Architects
# UT Austin, 2001
ACES Building
Cost:Impossible to find consistent numbers. $38 Million? (just construction?)
Space: 180K GSF, with 15GS basement, 109K ASF
CS 41%, ECE 27%
Major Donor:The O'Donnell Foundation paid for the whole thing.
Architect:Susman Tisdale Gayle
# Harvard, 1999
Maxwell Dworkin
Construction Cost:$26M (from unreliable source)
Space: 80K GSF, 51K ASF (as propposed)
Major Donors: $15M Bill Gates, $10M Steve Ballmer ($5M of Gates' donation when to a chair)
# Berkeley, 1996
Soda Hall
Project Cost: $35.5 million (entirely from private gifts)
Space: 100K GSF, 60K ASF (40 faculty offices)
Major Donors: $16M Charles and Hellen Soda, $5M Hewlett Packard Foundation
named rooms
initial specifications
Talk on the planning of the building
breakdown of space usage
Carlo Sequin was chair of building committee.
Planning started in the mid 80s
# Stanford, 1996
Gates Computer Science Building
Project Cost: $38.4 Million
Construction Cost: $26 Million
Space: 49K ASF (original plan)
Major Donors:$6M Bill Gates
# Princeton, 1993
CS Building
# Cornell, planning
2003 Strategic plan calls for a new building
Glossary
# ASF: Assignable square feet
# GSF: Gross square feet
# BOMA Standard: a standard for measuring square footage of rentable space specified by the Building Owners and Managers Association (typically slightly less than GSF).